Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73354 REL 46: 2008-527-00 EXP ZONE 6 FISHERIES JOHN DAY REPROGRAMMING 2020
Project Number:
Title:
Zone 6 Fishery (Prosser Hatchery Upgrades)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mainstem - 100.00%
Contract Number:
73354 REL 46
Contract Title:
2008-527-00 EXP ZONE 6 FISHERIES JOHN DAY REPROGRAMMING 2020
Contract Continuation:
Previous: Next:
73354 REL 33: 2008-527-00 EXP ZONE 6 FISHERIES CRITFC ACCORD PROJECT
  • CR-348670: 2008-527-00 EXP ZONE 6 FISHERIES SUPPORT 2022
Contract Status:
Closed
Contract Description:
The objective of the CRITFC Zone 6 Fisheries Accord Project is to address in-place, in-kind mitigation for losses due to the construction and operation of John Day and The Dalles dams by reprogramming existing production. Specifically, the project aims to help adjust the current stock mix of fall Chinook from the current 50:50 URB to Tule ratio to the target 75:25 URB to Tule ratio (In-kind), and to move fall Chinook releases to areas impacted by the construction of the two dams, thereby maximizing transit of returning adults through the Zone 6 fishery (In-place).
Account Type(s):
Expense
Contract Start Date:
09/01/2020
Contract End Date:
08/31/2021
Current Contract Value:
$83,309
Expenditures:
$83,309

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Coordinate with BPA staff on environmental compliance A: 165. Environmental Compliance -- Assist BPA EC lead with NEPA/ESA 08/31/2021 08/31/2021
Hold and attend meetings with regional tribal fishery staffs to achieve tribal consensus. B: 189. Coordinate with tribal staff to develop consensus and planning for the Zone 6 Fisheries Project 08/31/2021 08/31/2021
Hold and attend regional hatchery management and coordination meetings C: 189. Assist regional hatchery management processes and committees 08/31/2021 08/31/2021
Council Coordination D: 196. Prosser Upgrades for Zone 6 Fisheries John Day Reprogramming 08/31/2021 08/31/2021
Selection of design contractor E: 122. Prosser Upgrades for Zone 6 Fisheries John Day Design Contracting 08/31/2021 08/31/2021
Effective implementation management and timely contract administration F: 119. Project/Contract Administration 08/31/2021 08/31/2021
Complete and Upload Progress Report G: 132. Zone 6 Fisheries CRITFC Accord Project Progress Report 9/01/2019 to 8/31/2020 01/31/2021 03/31/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 196 Council Step Process

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance -- Assist BPA EC lead with NEPA/ESA
B 189 Coordinate with tribal staff to develop consensus and planning for the Zone 6 Fisheries Project
C 189 Assist regional hatchery management processes and committees
D 196 Prosser Upgrades for Zone 6 Fisheries John Day Reprogramming
E 122 Prosser Upgrades for Zone 6 Fisheries John Day Design Contracting
F 119 Project/Contract Administration
G 132 Zone 6 Fisheries CRITFC Accord Project Progress Report 9/01/2019 to 8/31/2020
H 185 Quarterly Status Reports